A Century-Old Pipeline Restored With HydraTite

A Century-Old Pipeline Restored With HydraTite

Market

Drinking Water

Challenge

Inspection of a cast-in-place conduit from the early 1920s revealed 13 joints in poor condition, three of which had developed active leaks. This pipe was approximately 90″ in diameter and was not perfectly concentric, incorporating a slightly flattened invert. A solution was needed quickly, that would cause minimal disturbance and downtime.

Several images of a large diameter pipe
A dark large pipe
An invert of a large-diameter pipe

Engineered Solution

13 Extra-Wide HydraTite Seals were chosen as the solution to eliminate the leaks.

Scope

First, the water was pumped out. Next, the surface of the pipe had to be prepared near the pipe. Debris was cleared away and concrete was used to smooth out the irregularities of this old pipe’s interior surface. Each seal was installed and then air tested. Some air tests revealed additional surface prep was required. These seals were deconstructed and more concrete was applied. The small crew had installed 13 seals that each passed the air test in only 8 days on site.

Several images of technicians installing HydraTite in a large diameter pipe
Several technicians installing HydraTite in a large diameter pipe
Several technicians installing HydraTite in a large diameter pipe
Several technicians installing HydraTite in a large diameter pipe
HydraTite installed in a large-diameter pipe
HydraTite being installed in a large-diameter pipe
HydraTite being installed in a large-diameter pipe
Several technicians installing HydraTite in a large diameter pipe

Solution

HydraTite provided a quick solution that was more targeted than lining, more long-lasting than grout, and less disruptive compared to dig and replace. These joints will be protected against infiltration and HydraTite will help prevent the formation of sinkholes.

Installation HydraTite in a large diameter pipe
Installation HydraTite in a large diameter pipe