Sealing 189 Joints In Three Box Culverts

Sealing 189 Joints In Three Box Culverts

Market

Stormwater

Challenge

Leaks were discovered in three culverts that redirected stormwater below a runway at an airport in Mississippi. A 50 by 150-foot portion of the runway began to sink in due to erosion. The leaks were found in two culverts that were 6 by 6-foot and a third culvert that was 4 by 6-foot. Joints had minor separation which was allowing water, soil, and plant life to enter the pipe. The airport patched the runway and intended to continue operations during any attempted repairs.

Several people standing near a culvert opening
Several technicians sitting inside a box-culvert
A box-shaped culvert
A small but very active leak inside a culvert
Several people standing near a culvert opening
Several technicians sitting inside a box-culvert
A box-shaped culvert
A small but very active leak inside a culvert

Engineered Solution

HydraTech provided custom-made HydraTite seals with anchors and corner forms for all the joints in the three culverts. HydraTech also manufactured custom-made drill hole guides to speed up the anchor drilling.

Scope

Over several months, three box culverts were rehabilitated. In these culverts, there were 189 joints sealed. One aspect that complicated the project was the frequent need to exit the culverts. If a plane was taking off, the water level started to increase, or if any unknown substance floated into the pipe, everyone had to vacate the job site.

The surface of the culvert near each of the joints was prepared for the seal installation by removing debris and chipping away mineral build-up. Then custom-made guides were used to drill the anchor holes, anchors were inserted into the holes, and the seal was then positioned between the anchors. Anchor plates were loosely put in position and the steel bands were expanded. Next, the anchor plates were tightened down and sealant was injected behind the corners of the seal. Finally, the anchors were trimmed down to ensure a minimal profile.

Technicians drilling holes in the walls of a box-culvert
A rubber seal positioning over a culvert joint
Anchor holes drilled on either side of a box-shaped culvert joint
A technician adjusting hold-downs
Technicians drilling holes in the walls of a box-culvert
Anchor holes drilled on either side of a box-shaped culvert joint
A rubber seal positioning over a culvert joint
A technician adjusting hold-downs
Technicians drilling holes in the walls of a box-culvert
Anchor holes drilled on either side of a box-shaped culvert joint
A rubber seal positioning over a culvert joint
A technician adjusting hold-downs

Solution

HydraTech provided customized seals to eliminate leaks in failing joints. These 189 joints will be fortified against leaks for much longer than if they had been repaired with a short-term repair such as grout.

A technician adjusting the hold-downs over a HydraTite seal
Technicians working inside a box-culvert, installing internal pipe joint seals over the joints
A technician walking through a box-shaped culvert

More On This Project